Current Status of Work


Project in Brief

Location

Village NaviPardi, Ta. Kamrej, Surat, Gujarat

Name of the SPV

Shanti Integrated Textile Park Pvt. Ltd

Area

48.16 acres

Activities

Spinning, Weaving, Knitting, Technical Textiles, Garmenting & Embroidery

Units

45

Project Cost as Approved by PAC under SITP

Rs 104.12 Crs

Expected Employment

2,777

Expected Total Investment

Rs 404.53 Crs

Expected Turnover

Rs 526.86 Crs

Government of India Grant

Rs 40 Crs

Date of Approval of Project by PAC

20th Sep. 2014

Release of GoI Grant

 

1st Instalment

Rs 4.00 Crs released on 24th Feb. 2015

2nd Instalment

Rs 4.00 Crs released on 31st Dec. 2016

3rd Instalment

 

4th Instalment

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Approvals/Clearances

Department

Status

Expected Date

GPCB, ENVIRONMENT CLEARANCE

Received on 27/05/2016

 

IRRIGATION,WATER SUPPLY

PROVISIONAL APPROVAL RECEIVED DATED:- 29/05/2015

 

DGVCL, ELCTRICITY

APPROVAL OF POWER RECEIVED ON : 15/12/2015

 

 

External Infrastructure

 

Infrastructure

Capacity/Distance

Status

Expected Date of Completion

Approach Road

 

 

 

Water Supply

Requirement:2 MLD

Source: CANAL

PROVISIONAL APPROVAL RECEIVED, DATED:- 29/05/2015

 

Power Supply

Requirement: 66 KV Substation

Source: DGVCL

APPROVAL OF POWER RECEIVED ON : 15/12/2015

APPLIED FOR 66 KV SUBSTATION AND EXPECTED APPROVAL JULY - 2017

 

Financial Progress

S.NO.

Components

Project cost as approved by PAC

(Rs in Crs)

Actual expenditure incurred

(Rs in Crs)

Physical Progress in %

1

Common Infrastructure

56.42

18.74

33.21%

2

Common Facilities

7.83

-

-

3

Factory Buildings

39.88

-

-

 

Project Cost eligible under SITP

104.12

18.75

18.00%

 4

Land

35.0

35.43

100 %

5

Design Engineering & Supervision Fees

1.50

0.87

58%

6

Preoperative & Other Expenses

10.08

3.27

32.44%

7

FD

 

1.05

-

 

Total Cost Incurred

 

59.37

-

 

Bank Balance( TRA-1+TRA-2+Current account)

 

4.07

-

 

Total Project Cost (Including Bank Balance)

150.70

63.47

42.11 %

 

Completed Packages

 

Package No 201A & 201B - Site Cleaning, leveling & Filling of Soil

 

Package No 203C - Construction of Culvert over Canal

 

Package 202 - Construction of Compound Wall

 

Current Packages

Current Site Visuals